Client: Holcim Azerbaijan

Contractor: HECOTEC LLC

Scope of Work:

  • Cleaning of accumulated material around 2 clinker material transitions before starting the work
  • Cutting and removal of worn iron sheets from the material transitions and aeronovs
  • Welding of new iron sheets in place of the removed old iron sheets
  • Bending of sheets with a specific thickness to the given radius
  • Installation and welding of two 16mm iron sheets, bent to a 1800mm radius, into the material transitions
  • Cutting and removal of worn iron pipes in the filter’s air pipes
  • Installation of new iron pipes in place of the cut and removed pipes
  • Completion and handover of the project.
  • Carrying out handover works related to the completion of the project