Client: Holcim Azerbaijan

Contractor: HECOTEC LLC

 

Scope of Work:

  • Project Management and Project Planning
  • Project Data & Document Management
  • Development of the Project Specific Construction, QA/QC, and HSE Documentation
  • Procurement of the materials
  • Mobilization
  • Installation of a scaffold on the gas pipe where the compensator will be replaced
  • Cutting out the old compensator
  • Removing the flanged pipe by cutting it from both sides
  • Preparation of new flanged pipes according to the drawing
  • Installation of newly made flanged fitting pipes in place of removed old flanged pipes
  • Installation of a new compensator
  • Dismantling and removing the scaffold installed on the upper part of the gas pipe of VRM
  • Demobilization
  • Final documentation and project delivery