Client: NORM Cement Plant

Contractor: HECOTEC LLC

 

Scope of Work:

  • Project Management and Project Planning
  • Project Data & Document Management
  • Development of the Project Specific Construction, QA/QC, and HSE Documentation
  • Procurement of the materials
  • Mobilization
  • Cutting and removing plasterboard lining on the ceiling along the wall line in order to ensure that the wall rises up to the concrete ceiling
  • Preparation and installation of the frame from C profiles according to the drawing.
  • Insulation of profile gaps with 100 mm mineral stone wool (without gaps). Density ≥100kg/m³
  • Application of SoundGuard Membrene 3.9 S soundproofing material on the side of the wall intended for double plasterboard before the second layer of plasterboard.
  • Plastering of lining and facing plaster on the wall from both sides, painting of the wall
  • Covering the wall on both sides with MDF + Membrane coated material suitable for existing pans.
  • Demobilization
  • Final documentation and project delivery