Client: NORM Cement Plant

Contractor: HECOTEC LLC

 

Scope of Work:

  • Project Management and Project Planning
  • Project Data & Document Management
  • Development of the Project Specific Construction, QA/QC, and HSE Documentation
  • Procurement of the materials
  • Mobilization
  • Dismantling the existing filter in the cement mill
  • Dismantling the filter in the unloading area and bringing it to the vicinity of the cement mill
  • Cutting and shortening the existing hopper and replacing the part where the hopper body is joined by welding with a bolted joint
  • Modification works of the existing metal structure
  • Removing the valve from the existing filter and installing it on the new filter
  • Installation of suction boilers (chutes) according to the drawing
  • Dismantling and removal of existing air belts, replacement with new ones and modification works
  • Demobilization
  • Final documentation and project delivery